top of page

Holsworthy Structural Inspections, Moorebank NSW

Structure Inspection

The Australian Defence Force relocated services to the Holsworthy Army base to release land for a new Intermodal facility in Moorebank NSW. This included a museum, Chapel, educational and accommodation facilities.

 

Teleo was engaged by one of the fabricators providing steelwork for this project. Teleo was to undertake periodic inspections of the steelwork as it was being erected to ensure it complied with the design and was suitable for the next phase of construction. Inspections included assessing the steel was ready to install the concrete floors and steel cladding.

 

Teleo provided regular inspections, over a 2 year period, of steel work as it was being erected for compliance to drawings. The job required approximately 1500t of steel to be inspected. On completion, Teleo issued the final BCA compliant engineering certification for the steelwork installation in each building inspected.